smuteye.comC H Cox Buildings

REPAIR STATUS

Select from the list below to see the status of each item.

508 South Lawrence 

11 October 2000 -- See accompanying report.

Steel DoorsInstalled

Cleanup Underway

29 September 2000

Brickwork


South side windows and door bricked up.  Clean-up is underway.


Rear openings bricked up.  Old brick is still rough.
Trash is being cleaned up.  


Brick fence between building and garage.

 

22 September 2000
1 -Materials are on site.  
2 - The lower rear windows have been bricked up.  
3 - Rain on Friday slowed extension of bricks to garage.

Back to TopBack to Top

 

522 South Lawrence

Roof / Ceiling
See accompanying report.


After - 11 October 2000


Before - 7 October 2000

Outside Corner

After
29 September 2000
Repaired Brickwork on Corner

Before
   
   


28 October 2000
Steel Plate Installed


Work in Progress
"Art Shot"

 

Back to TopBack to Top

Back to CH Cox Buildings Main

Improvement Group, Inc.
PO Box 104
Montgomery, AL 36106

Or email:  majorcox@smuteye.com

Return to Real Estate Page | Main Page

 

You are visiting www.smuteye.com, a virtual rural community.
  

Comments:  info@smuteye.com
Copyright 2001-08.  All Rights Reserved.

Web Site Design: TEAM Support, Inc.
www.team-support.com

farm.gif (1224 bytes)
Contact us at: 

editor@smuteye.com

Last update:  Monday, September 01, 2008

Back to the Main Page